Senegal's international airport to open in December 2017

Posted 17 February 2017 · Add Comment

Initially planned to open in December 2015, the launch of Senegal's Blaise Diagne International Airport (AIBD) is now scheduled for Q4 2017.

One of the West African country’s most ambitious projects, Senegal’s AIBD is designed to become a major hub for the region.
"The airport is vital for the economic development of Senegal and that is why we are doing everything possible to finish it," sayid Abdoulaye Mbodji, the project’s director general.
The Senegalese capital, Dakar, comprises 3% of the territory, 25% of the population and 80% of the economic activity of the country and the new airport is designed to allow both enhanced management of the territory and the creation of a new economic focus. It will also be a pillar for the development of tourism and exports, especially fresh produce.
Construction began in 2007 and by 2013 the project was 54% complete. By December 2014, more than 80% of the work was finished.
However, construction stopped early in 2016 due to a financial dispute between the Senegalese State and prime contractor.
The latest financial scheme features a development pool of eight banks led by the African Development Bank (AfDB) and the Islamic Development Bank (IDB). This solution also features the appointment of a Turkish consortium featuring specialists in the construction industry, Summa and Limak, and the Senegalese authority said it is now confident that the airport will be operational by the end of 2017.

According to the project’s director general, remaining work includes the construction of the new freight warehouse; implementation of procedures; and the electrical wiring of the new terminal.

The AIBD covers an area of 4.500 hectares of which around half has been utilised so far. It features a main terminal of 4,200m² on two levels that will have a capacity of around three million passengers per year, increasing to 10 million by 2035.
A second terminal, specifically for freight operations, will have an annual capacity of 50,000 tonnes. A third terminal will be used for the transport of Hajj pilgrims.
The airport will have a main 3,500mx75m runway designed to accommodate long-haul aircraft such as the A380 and B787. The airport's infrastructure be capable of dealing, simultaneously, with 50 airliners including 26 wide-bodies, six single-aisle and 18 GA.
Certification is already well underway and it’s anticipated that it will be completed by the end of 2017, enabling all flights to be transferred from the existing Leopold-Sédar-Senghor facility.
 

* required field

Post a comment

Other Stories
Advertisement
Latest News

EgyptAir on cloud nine with latest 737-800 delivery

EgyptAir has received its ninth and final Boeing 737-800NGs on a lease deal from Dubai Aerospace Enterprise (DAE) and valued at $864 million. All nine were handed over during in the course of the past year.

GECAS takes delivery of its 394th and last Next-Generation 737

Culminating a 20-year history of new orders for the type, GECAS has received its 394th and final skyline order of Boeing's Next Generation 737. Just over a month prior to Boeing delivering its first 737 MAX to GECAS in January, the lessor

Jambo makes a Dash for expansion

As low-cost carriers develop across Africa, Githae Mwaniki talks to Jambojet CEO, Willem Hondius, about the airline's operation plan in Kenya and the East African region.

Pilatus obtains PC-24 Type Certificates

Pilatus has obtained type certificates from the European Aviation Safety Agency (EASA) and the US-American Federal Aviation Administration (FAA) for the first ever Swiss business jet.

Arik Air may resume London flights

The Federal Government of Nigeria is in talks with the UK on how Arik Air will return to the London route, reports The Afritraveller.

Airbus BizLab starts its third season Nigerian start-up among 12 selected for development

Airbus BizLab, the start-up accelerator of the global corporation Airbus is hosting twelve new start-ups from around the world including Nigeria over a six-month period at its facilities in Hamburg and Toulouse, during which they

Aviation Africa SK18418
See us at
Aviation Africa BT18418Global Aerospace BT28218